A construction contract is not a longer vendor contract. It carries lien exposure, licensure consequences, retainage, warranty periods and a payment process that can leave an association paying twice for the same work. Use this checklist on the proposed agreement, with the engineer's or architect's specification open beside it, before the board votes to sign.
Work through the sections in order. The citation under an item shows where the requirement comes from. Read this together with our guidance on engineering and construction contracts and, once work begins, the Major Project Oversight Checklist.
The contractor and the license
- Check the classification against the actual work. A general contractor's license does not carry roofing, and a roofing license does not carry structural concrete.
- A common pattern is a licensed individual qualifying a company they no longer work for. The board finds out when the permit is refused.
- A contract entered into by an unlicensed contractor is unenforceable in law or in equity by the unlicensed contractor, and no lien or bond claim exists in its favor. That is a defense, not a repair. The association is still left with unfinished or defective work and no solvent party to fix it.§ 489.128
- Architect and engineer services are exempt from the bidding sections. The construction work itself is not.Condominium and cooperative 5% of the total annual budget including reserves; HOA 10%. § 718.3026(1); § 719.3026(1); § 720.3055(1)
Scope, drawings and specification
- "Per plans and specs" without identifying which revision is how a contractor prices an earlier, cheaper version.
- Most contractor forms put their own proposal on top. That single line can delete half the engineer's requirements.
Price, allowances and change orders
- Boards routinely believe they signed a lump sum when the form is cost plus with no cap.
- Allowances for concrete spall repair and rotten sheathing are where the number the board approved becomes the number the association pays.
- Hidden conditions behind stucco and under decks are normal on Southwest Florida buildings. The clause that matters is the one that makes the contractor tell you before spending your money.
Schedule, delay and liquidated damages
- A liquidated damages figure set far above actual loss is attacked as a penalty and may not be enforced. A figure the board cannot explain is worth less than one it can.
- Repairs required by a phase two milestone inspection report must commence within 365 days of the report — § 553.899
Payments, retainage and lien releases
- § 713.20(4)
- A release from the contractor does not release the lien rights of a subcontractor the contractor has not paid.
- A person may not require a lienor to furnish a waiver or release different from the forms in § 713.20(4) or (5)
- A right to claim a lien may not be waived in advance; it may be waived only to the extent of labor, services or materials already furnished — § 713.20(2)
- § 713.20(5)
Notice of commencement, notices to owner and the pay-twice risk
- § 713.13
- The statutory warning is blunt: payments made after the notice of commencement expires are improper payments and can result in paying twice for the same improvements.§ 713.13
- A lienor other than a laborer must serve a notice to owner before commencing or not later than 45 days after commencing to furnish labor, services or materials — § 713.06(2)
- This is the whole of the pay-twice protection. An association that pays the contractor in full without collecting lienor releases can be liened by an unpaid subcontractor and end up paying the same money twice.
- § 713.06(3)(d)
- A payment bond that is not properly recorded and referenced does not give the association the protection the board thinks it bought.§ 713.23
Warranty, insurance, bonds and indemnity
- A roofing manufacturer's warranty is often void unless the manufacturer inspected and the association registered it. Ask for the certificate, not the brochure.
- This applies to private construction contracts, not only to public projects. An indemnification provision in a construction contract that lacks the required limitation is unenforceable, so an association that accepts a bare indemnity clause may have no indemnity at all.§ 725.06(1)
Close-out
- § 713.06(3)(d); § 713.20(5)
- § 718.111(12); § 719.104(2); § 720.303(4)
Statutes and authorities referenced
- § 489.128, Fla. Stat. (contracts of unlicensed contractors unenforceable by the contractor)
- § 713.06, Fla. Stat. (notice to owner; contractor's final payment affidavit)
- § 713.13, Fla. Stat. (notice of commencement)
- § 713.20, Fla. Stat. (waiver and release of lien; statutory forms)
- § 713.23, Fla. Stat. (payment bond)
- § 725.06, Fla. Stat. (indemnification in construction contracts)
- § 553.899, Fla. Stat. (milestone inspections; commencement of phase two repairs)
- § 718.3026(1), § 719.3026(1), § 720.3055(1), Fla. Stat. (competitive bidding thresholds)
- § 718.111(12), § 719.104(2), § 720.303(4), Fla. Stat. (official records)
Contact Hamilton Mikes
Hamilton Mikes drafts and negotiates construction contracts for Southwest Florida associations undertaking roofing, concrete restoration, structural and milestone-driven repairs, and advises boards on lien exposure and payment controls during the job. Call 239-594-7227 or visit our Construction page.