Post-Hurricane Board Checklist: The First Days, in the Order They Have to Happen

The first days after a Florida hurricane, in order: safety, habitability, emergency powers, mitigation and the damage survey, with the statute beside each step.

In the first days after a storm the board will be asked to decide things faster than it can think about them. Almost all of the damage a board does to itself in that window comes from three places: letting people back in before anyone qualified said it was safe, signing something to make a contractor go away, and moving the debris before it was photographed. This checklist keeps those three from happening.

Download the PDFThe PDF is a designed, printable copy for the board packet, the bulletin board or your meeting portfolio. On screen, you can tick the boxes below; nothing you tick is saved or sent anywhere.

Work it in order. The board's emergency powers exist, but they are narrower than most boards assume and they expire. Where an item applies to one chapter only, it says so. For the underlying law see our guide to post-hurricane board duties.

One rule governs everything below: write down what you decided, when, on whose advice, and who voted for it. A board acting under emergency powers is still a board acting, and the record of the decision is what defends it a year later.

The first hours: safety and access

  • § 718.1265(1)(g); § 719.128(1)(g); § 720.316(1)(g)
  • Condominium and cooperative boards may require evacuation of the property in the event of an evacuation order in the locale, and the statute gives immunity for owners who refuse to leave. An HOA board has no such power.§ 718.1265(1)(h); § 719.128(1)(i); § 720.316(1) contains no evacuation power

Habitability, and who is allowed to decide it

  • The board's power is to determine habitability based upon the advice of licensed professionals or emergency management or public health officials, not on its own judgment. § 718.1265(1)(i); § 719.128(1)(h)
  • § 720.316(1)(h)
  • "The east tower is fine" is a sentence that has to come from the engineer's letter, not from a director standing in the parking lot.
  • § 718.1265(3); § 719.128(3); § 720.316(3)

Emergency powers: invoking them and papering them

  • The powers are keyed to a declared state of emergency in the area encompassed by the association. Without that, the board is operating on ordinary authority.§ 718.1265(1); § 719.128(1); § 720.316(1)
  • Meetings by telephone or real-time electronic means with notice in any practicable manner. § 718.1265(1)(a); § 719.128(1)(a); § 720.316(1)(a)
  • A resolution that says the board acts under § 718.1265(1)(j) and (1)(k) is far harder to attack than one that says the board is exercising its emergency powers.
  • § 718.1265(1)(l); § 719.128(1)(l); § 720.316(1)(j)
  • Chapter 720 has no ratification mechanism in the emergency-powers section or in the meeting provisions. HOA boards should still re-approve emergency actions at the next regular meeting as a matter of practice.§ 718.112(2)(c)1.; § 719.106(1)(c)
  • § 718.1265(2); § 719.128(2); § 720.316(2)

Mitigation and the duty to prevent further damage

  • The policy imposes a duty to protect the property from further damage. Delay between the storm and the extraction is the gap a carrier uses to reduce a claim.
  • Mitigating further damage, injury or contagion, including contracting for debris removal and preventing or mitigating the spread of fungus or contagion, is an express emergency power. § 718.1265(1)(j); § 719.128(1)(j); § 720.316(1)(i)
  • Mitigation is usually paid differently from reconstruction. Mixing them in one invoice makes both harder to recover.
  • Use it sparingly and document necessity for each unit. An HOA board has no equivalent power under § 720.316.§ 718.1265(1)(k); § 719.128(1)(k)

The damage survey, before anything is moved

  • Matched before-and-after pairs of the same view are the strongest evidence an association can produce. See insurance claim documentation.
  • Fasteners, connectors and sections of failed roof covering can decide a construction defect or product claim later. Once they are in the debris pile they are gone.
  • The hold reaches directors' personal phones where association business was conducted. See litigation hold and record preservation.

Debris, utilities and security

  • § 718.1265(1)(e); § 719.128(1)(e); § 720.316(1)(e)
  • In the week after a storm, uninvited crews will be on the property. A sign-in log is also your record of who was where when something goes missing.

Emergency contracting, and its limits

  • Assignment of post-loss benefits is prohibited for residential and commercial property policies issued on or after January 1, 2023, and the attempt is void. § 627.7152(13)
  • § 489.128
  • Emergency powers let a board act quickly. They do not repeal the bidding provisions, and a board that skipped bids should say in the minutes why the emergency required it.§ 718.3026(1); § 720.3055(1)
  • The firm that dried the building out should not end up holding the reconstruction by default. See our emergency contractor review checklist.

Owners, and what to hold until counsel and the adjuster are in

  • § 718.111(11)(f) for condominiums; the declaration and proprietary lease for HOAs and cooperatives
  • An assessment announced on a guess and revised twice is how a board loses the room. See post-storm special assessments.

Statutes and authorities referenced

Contact Hamilton Mikes

Hamilton Mikes works with Southwest Florida boards in the first days after a storm on habitability, emergency authority, mitigation contracts and the record that has to support all three. Call 239-594-7227 or visit our Disaster Recovery page.

We're ready to help

Speak with a Florida community association attorney

Tell us about your association and the legal challenge you are facing. Our team is ready to listen, respond, and help you identify a clear path forward.

239-594-7227 Info@HamiltonMikes.com
Hamilton Mikes, P.A.
8850 Terrene Court, Suite 110
Bonita Springs, FL 34135
How would you like to be contacted?

Fields marked * are required. Or call 239-594-7227.