After a storm the usual procurement process is not available. There is no time for three bids, references and a committee. What is still available is fifteen minutes of checking that eliminates most of the operators who will cost the association money. This checklist is what those fifteen minutes should cover, and what the paperwork has to say before anyone signs it.
Nothing here requires a lawyer to perform. It requires someone to do it before the crew starts rather than after, and to write down what they found. Where an item exists because a statute says so, the citation is under it.
The roofing rules in section 489.147 deserve particular attention. They were written for storm chasing, they carry real penalties, and a contractor who breaks them in front of you is telling you what the rest of the job will look like. For the wider contracting picture see vendor contract review and restoration contracts.
Licence: check it yourself, before anything else
- A business organization is unlicensed unless it has a primary or secondary qualifying agent licensed for the scope of work. A crew working under someone else's licence is the classic post-storm problem.§ 489.128(1)(a)
- Unenforceability protects the association against the contractor's claim. It does not get back money already paid, and it does not repair the building.A contract entered into on or after October 1, 1990 by an unlicensed contractor is unenforceable in law or in equity by the unlicensed contractor; the rights of other parties to enforce contract, lien or bond remedies are unaffected. § 489.128
- An owner-pulled permit moves the code liability to the association and is a standard sign the contractor cannot pull one.
Insurance: verify it, do not accept a copy
- An injured uninsured worker on association property is the association's problem. Ask specifically about subcontracted crews, which is where the coverage gap usually sits.
The paperwork you refuse to sign
- A policyholder may not assign, in whole or in part, any post-loss insurance benefit under a residential or commercial property insurance policy issued on or after January 1, 2023; an attempt to do so is void, invalid and unenforceable. § 627.7152(13)
- "We will do whatever insurance pays" is not a price and is not a scope. It guarantees a dispute about both.
Money: deposits, draws and what is lawful
- A contractor who receives more than 10 percent of the contract price as a down payment for residential real property work must apply for necessary permits within 30 days after the payment and start the work within 90 days after all necessary permits are issued, absent the owner's agreement otherwise. § 489.126(2)(a)
- Violations of § 489.126(2) carry criminal penalties graduated by the amount received, from a first-degree misdemeanor under $1,000 to a first-degree felony at $200,000 or more. § 489.126(5)
The roofing rules, which are the ones being broken
- A communication encouraging a consumer to contact a contractor or public adjuster about a roof damage insurance claim is a prohibited advertisement unless it carries the required disclosures in at least 12-point type and at least half the size of the largest font used.§ 489.147(1)
- § 489.147(1)
- A contractor may not offer a residential property owner a rebate, gift, gift card, cash, coupon, or waiver of any insurance deductible. § 489.147(2)(b)
- § 489.147(2)(c)
- That is adjusting. A contractor who is not a licensed adjuster or an attorney may not do it, and a contractor who does it is usually building toward an assignment or a padded scope.§ 489.147(2)(d)
- Providing an insured with an agreement authorizing repairs without providing a good faith estimate of the itemized and detailed cost of services and materials is a prohibited practice. § 489.147(2)(e)
- A residential property owner may cancel a contract to repair or replace a roof without penalty within 10 days after execution or by the official start date, whichever comes first, where the contract was entered into within 180 days of an event that is the subject of a declaration of a state of emergency. § 489.147(6)(a)
- The offer is the fraud. A board that accepts it is on the wrong side of the same statute.
Written scope and price, even when hurried
- Post-storm disputes are almost always about change orders nobody signed. Say in the contract that unsigned extras are not payable.
Liens and releases, from the first dollar
- § 713.13(1)(a)
- § 713.02(5)
- § 713.20(4)
- § 713.20(5)
- A person may not require a lienor to furnish a lien waiver or release different from the forms in § 713.20(4) or (5). § 713.20(6)
- A right to claim a lien may not be waived in advance; a lien right may be waived only to the extent of labor, services or materials furnished, and an advance waiver is unenforceable. § 713.20(2)
Price gouging, out-of-state crews and the authority to sign
- It is prima facie evidence of an unconscionable price that the amount charged represents a gross disparity between the price and the average price at which that commodity was sold or offered in the usual course of business during the 30 days immediately prior to the declaration of a state of emergency, unless the increase is attributable to additional costs incurred or to regional, national or international market trends. § 501.160(1)(b)
- It is unlawful to rent or sell or offer to rent or sell at an unconscionable price within the area for which a state of emergency has been declared; the prohibition runs for the period of the initial declaration, not to exceed 60 days, and may be extended by executive order. § 501.160(2)
- "Commodity" includes goods, services, materials, merchandise, supplies, equipment, resources or other articles of commerce, including those necessary for consumption or use as a direct result of the emergency. § 501.160(1)(a)
- § 718.1265(1); § 719.128(1); § 720.316(1)
- § 718.112(2)(c)1.; § 719.106(1)(c). Chapter 720 has no equivalent provision.
Statutes and authorities referenced
- § 489.147, Fla. Stat. (prohibited advertisements and practices, roof repair contracts)
- § 489.128, Fla. Stat. (contracts of unlicensed contractors unenforceable)
- § 489.126, Fla. Stat. (moneys received by contractors; permit and commencement deadlines)
- § 627.7152(13), Fla. Stat. (prohibition on assignment of post-loss benefits)
- § 501.160, Fla. Stat. (unconscionable prices during a declared state of emergency)
- § 713.13, § 713.02(5), Fla. Stat. (notice of commencement; small-contract exemption)
- § 713.20, Fla. Stat. (waiver and release of lien; statutory forms)
- § 718.3026(1), § 720.3055(1), Fla. Stat. (competitive bidding thresholds)
- § 718.1265, § 719.128, § 720.316, Fla. Stat. (emergency powers and authority to contract)